Saturday, July 26, 2014

2nd Floor Framing

The framers rolled the floor joists for the second floor and erected the second floor walls and stair column walls this week.  BMC Lumber pre-cut and bundled many of the walls.  This is accelerating the framing.  It was fun to walk on the second floor and see the views.

Basement Floor Pour


At the end of the week, the concrete floor in the basement was poured.  Luckily, the thunderstorms held off until the concrete could set up. 

Crane and Steel

The week started with a crane placing a 50' steel beam in the center of the first floor, along with a glue lam header in the garage ceiling.  They are designed to support the floor joists on the  second floor. 

Sunday, July 20, 2014

We Have Walls!

The framing crew came on site this week and by Friday they had the first floor walls up.  It's great to see the outline of the garage doors on the front (left photo) and sliding glass doors on the rear (right photo)of the first floor.  Ground iron also passed inspection this week.

Wednesday, July 16, 2014

We Have a Foundation!

The foundation was completed over the past week.  The walls were dampproofed and a french drain installed on the north side to relieve hydraulic pressure against the foundation walls.  Now that the foundation is backfilled, it gives us a feel for the position of the home on the lot.  Sleeves for the gas and electric service were also installed, along with the water line.  Framing and ground iron (plumbing under the slab) commences this week.


Saturday, July 5, 2014

Foundation Walls Are Poured

Finally!

The foundation walls were poured this week. Another opportunity to have fun with the concrete pumper.

Hope everyone enjoys the 4th of July holiday weekend.  

UPDATE: Forms came off and the walls look great!