Schedule

2014

March 
  • Donations of home materials to Habitat for Humanity
  • Asbestos removal
  • Tree trimming
 April
  • Weed control
  • Application for building permit
May
  • Demolition of original structure
  • Tree removal
  • Excavation for foundation
  • Foundation work 
June
  • Soils Testing and Foundation Engineering
  • Foundation work 
July
  • Foundation completion
  • Dampproofing and French Drain
  • Foundation backfill 
  • Ground iron and basement floor flatwork
  • Framing
August
  • Framing 
September
  • Roof installation
  • Window installation
  • Plumbing rough-in
  • Electrical rough-in
  • HVAC rough-in
  • Fireplace installation
  • Exterior finishes (cedar siding)
October
  • Electrical rough-in
  • Metal staircase installation
  • Exterior finishes (stucco and painting)
  • Roof flashing
  • Insulation
November
  • Drywall installation
  • Stucco Completion
December 

...

January
  • Projected completion