Sunday, June 29, 2014

Foundation Wall Forms

This week, the foundation contractor returned to setting the wall forms and installing the rebar in the walls.  We are on schedule for inspection and concrete pouring for the walls this coming week. 

Meanwhile, our framing contractor is helping us manage the delays over the past month by pre-cutting our lumber in the lumber company's computerized factory.  The lumber for various wall sections will be arriving cut, bundled and labeled so the framing crew can work quick and make up some time in our schedule. 

We hope that the rainbow over Golden we saw on Friday night bodes well for the upcoming construction activities.