Sunday, October 12, 2014

Prepping for Stucco



The major work this past week was preparing the house for stucco.  The crew worked through last weekend to attach paper and lathing to exterior walls.  Their work passed inspection on Thursday and the stucco scratch coat will be applied this upcoming week.  Meanwhile, we walked the house with Karen and Paul, our architects, John, our electrician, and Mark on Wednesday and finalized the electrical and lighting choices so the electrical rough-in can be completed.