We know. We have not uploaded a new post for over 2 weeks. We blame it on travel and deadlines at work. Despite this, the construction has achieved several milestones. Most notably, the mechanical, electrical, plumbing, and framing all passed inspection. With that, the insulation contractor installed all the insulation in the exterior walls and ceilings, and a few important interior walls (e.g., bathroom walls). Most of the insulation was blown in, which gives a higher R-value.
The insulation makes the house retain the heat from the sun during the day.