Sunday, December 14, 2014

All About Flooring


 Work this week was devoted to installing the entire wood flooring and continued installation of the tile.  Here's a picture of the tile in the front entrance.

Sunday, December 7, 2014

Wood Flooring and Tile

After completing the plastering of the drywall over the weekend, the installation of the wood floor started on Friday.  It is gorgeous - 6" wide planks of white oak from Coleman, WI.  Also, our tile contractor started installing the floor and bathroom tile.  He will be onsite for 2-3 weeks.   

Final Stucco


The final coat of stucco was applied last week and we can now see the final look of the house colors.  The grey stucco coloring was more taupe than we expected but it looks very good with the wood siding. 

Wednesday, November 26, 2014

Happy Thanksgiving

We have a lot to be thankful for this year.  Our family is healthy; Katie is graduating from the University of Colorado Denver next month; and the house construction has proceeded with very few, minor hiccups.  We solved one of those hiccups last Friday when Xcel finally connected the gas service.  After digging up the roadway three times, they finally set the gas meter and our furnace fired up.  We now have heat throughout the house.  This is important for we are priming and plastering the walls this week.  If all goes well, flooring installation will start next week.
 

We are looking forward to many celebrations in our new home, starting in 2015.

Happy Thanksgiving!

Tuesday, November 18, 2014

Hanging Drywall

The last week was bitter cold.  The arctic weather system kept high temps below 20 degrees for most days of the week.  But, Mark brought in heaters and our drywall crew was able to keep working.  They hung the drywall throughout the house and, now, we can really see the rooms.  We worried that the house would feel a lot smaller but that didn't happen.  The windows and high ceilings helped maintain the sense of large spaces.  Now, we need the weather to warm up so the drywall can be taped and mudded and the final stucco coat applied.  Fortunately, the sun is out this week and the snow is melting, both good signs.


Saturday, November 8, 2014

Sheetrock!

The sheetrock was delivered on Wednesday, all 400 sheets.  That's right, they loaded it into the house through the windows.  It adds at least 20,000 lbs to the house.  Our contractor will wait until all the sheetrock is hung before applying the final finish coat of stucco.  All that additional weight causes normal cracking in the stucco base layer.  The drywall crew started hanging the sheetrock on Thursday.  As they move
through the house, we can see the final size of each room.




Friday, November 7, 2014

It's Been a While

We know.  We have not uploaded a new post for over 2 weeks.  We blame it on travel and deadlines at work. Despite this, the construction has achieved several milestones.  Most notably, the mechanical, electrical, plumbing, and framing all passed inspection.  With that, the insulation contractor installed all the insulation in the exterior walls and ceilings, and a few important interior walls (e.g., bathroom walls). Most of the insulation was blown in, which gives a higher R-value.
The insulation makes the house retain the heat from the sun during the day.